Jahra Road Project mpc
Louis Berger pace

Phase 3 is located between the hospital road and Ghazali Bridge and consists of the units 9 to 20 of the main line and 4 ramps.Paste

Ramps JRG, JRH, JRI and JRJ are on- and off- ramps from the main line to the Jahra service roads. 

Actual work done in phase 3

Abutment 100%
Bridge piles 100%
Pile Caps 100%
Piers stem 100%
Piers crown 100%
Diaphragms 100%
Segment erection 100%